Navita Delivery Timeline

Quick Installation of Pomax: With a minimum of customization, you can be up and running in 12 weeks.

Configuration Workshop

One-day session on your configuration requirements, hardware infrastructure, access rights, etc.

Configuration Specification

The document that, after being agreed upon by both parties, serves as the basis for the entire project.

Pre-configuration

Handles all generic settings not specific to a given installation.

Client-Specific Configuration

Based on the Configuration Specification, this process implements the subset of Pomax's pre-built functions that will best meet your company's trading, risk management and logistics requirements.

Documentation

Navita will provide all documentation for your installation of Pomax, including all user and administrator manuals.

Installation

Navita then installs Pomax and all associated software on designated servers at the sites your specify.

Site Acceptance Testing

A significant project milestone, this step confirms that all aspects of the installation work according to spec on your site.

User Training

Navita Support is responsible for teacing the users you designate how to use and optimize Pomax for their work.

System Support Training

Of your designated IT personnel.

User acceptance testing

Supported by Navita.

Go-Live Support

Navita provides special Go-Live Support to your organization the day Pomax goes live.